FERC says the scoping notice for a sixth Rio Grande LNG train went out with a distribution error, and it has added one virtual session to a review that runs into 2027
The Commission is running an extra session because of a mistake it made.
That is the disclosure buried in a schedule notice for the Rio Grande LNG Expansion Project, which would add a sixth liquefaction train and a third marine jetty to a terminal already under construction on the Brownsville Ship Channel in Cameron County, Texas. The notice says it plainly. Due to an error in the distribution of the Notice of Scoping to the interested stakeholders on the mailing list, staff have decided to conduct one virtual scoping session. It does not say what the error was, who made it, or how many people it reached.
The session runs on 19 August, from 5 to 7 p.m. Central, on a conference line, with three minutes per speaker and a court reporter taking the record. Written comments are due by 5 p.m. Eastern on 31 August.
The project
Rio Grande LNG Train 6, LLC proposes about 6.03 million tonnes a year of additional liquefaction capacity, built entirely inside the terminal that is already authorized and under construction.
Construction would disturb about 303 acres for the train and its supporting infrastructure and about 22 acres for the new berth, plus roughly 383 acres of temporary offsite construction yards that the notice says would be restored. About 51 acres would be kept for permanent operation. In the water, construction would affect 28.7 acres of the ship channel. Once running, the addition would emit about 277 tons of nitrogen oxides a year, 7 tons of fine particulate matter, and 5.8 tons of hazardous air pollutants.
The clock
Pre-filing opened in March, with two sessions held in Port Isabel on 24 and 25 March, and the pre-filing scoping period expired on 8 April. The company has since filed its formal application, and the Commission issued its notice of application on 9 June.
Staff now plan a draft environmental impact statement in January 2027, with 45 days for comment, and a final statement on 25 June 2027. A 90-day deadline of 23 September 2027 then applies, and the notice is specific about whose deadline it is: it binds other federal agencies, and state agencies acting under federally delegated authority, that must issue the permits the project needs.